ASIAN Paints, Khandala, Pune Maharashtra 2011
 

The Paint Industry has been growing at a healthy rate over the past few years; Asian Paints is the market leader in decorative paints both distemper as well as emulsion paints. The company has a market share of over 65% of the decorative paints in India.

The main challenge in front of Interarch at this time was to finish the project in the stipulated time period along with high safety expectations of the client. Another challenge in front of Interarch was the extreme dimensions of the buildings required by client for manufacturing process and stacking of raw materials, the entire project has 18 buildings in totality had variable heights with buildings towering at those of up to 30 M and had clear spans of up to of 44 M. The total project consumed more than 3000 MT of steel for structural system and around 70,000 Sq. of roofing & sheeting was supplied and installed.

The entire pre-engineered steel was manufactured in Interarch Pantnagar plant and to overcome the shortness of time 3 shifts with over 150 workers & supervisor’s was started for nearly 2 months. Separate bays were created in the manufacturing plant to paint the rafters and beams as desired by the client. It took over 2 months to manufacture the steel and roofing system required.

Further, to save time no scaffolding were used and only electronic boom lifts were employed with specially trained manpower. For the first time safe roof access of 35 M high was created by Interarch of Pipe Structure and for safety inspection.

The client has also awarded Interarch Building Products for ensuring safe & healthy work environment at site. The client has also awarded Interarch Building Products for ensuring safe & healthy work environment at site.


Key Project Highlight
 
Project Name Asian Paints Ltd
Building Location Village Khandala, Pune Satara Road, Maharashtra
Building Usage Greenfield expansion projects for Asian Paints
Tonnage of building 3,000 MT
Roofing Supplied in MT 70,000 Sq. M
Value of Project 40 Cr.
Area of Project 65000 Sq. M
Important Feature of Project
Greenfield expansion projects for Asian Paints
Manpower Deployed: 500
Erection of Building : 3 months
Height of the Buildings : 30 M
44 M clear span
Total number of Buildings-18
Completion time of Project 8-10 month
Standing Seam Roof
High safety expectation of the client
Safety Award Won by Asian Paints Ltd
No scaffolding, only electronic boom lifts
International erectors from south east Asia were employed
Safe Roof access of 35 M height was created of pipe structures for inspection


Share my campaign If you find this information useful, please send us your feedback at: info@interarchbuildings.com
© Copyright 2010, all rights reserved with Interarch Building Products Pvt. Ltd.
visit us at: www.interarchbuildings.com, www.interarchinfra.com